We'd like to compare the advantages and disadvantages of different building formwork systems from different views in table.

Table 1: Advantages and Disadvantages of Formwork Systems
Items Plywood formwork Steel formwork Aluminium formwork Remarks
Material 18 mm thickness plywood 5–6 mm thickness steel plate 4 mm thickness 6061 - T6/6082 - T6 aluminium alloy light weight, high strength
Weight (kg) 10.5 80–85 18–22
Bearing capacity (kN/m2) 30 60 60
Early stripping formwork system not use, three set of formwork and three set of supporting employ, one set of formwork and three set of supporting employ, one set of formwork and three set of supporting efficient and convenient construction
Construction period more than 10 days per floor 4–5 days per floor 4–5 days per floor
Operation easier difficult easier
Cycle time 5 250 300 high reuse rate
Construction waste more general little
Maintenance lower high low
Efficiency low high higher
Application wall, column, beam wall wall, corner, beam, column, balcony, stairway, bay window, etc. standard, versatile
Structure quality rough surface smooth surface, fair-faced smooth surface, fair-faced high project quality
Plaster fee high none none
Recycle value low middle high high recycling value
Lifting tower don't need need don't need simple operation